3.9 kWp rooftop system 2022 - 3.9 kWp modules East/West, 3 kW inverter, 5kWh battery From Jul-2022 Installation in Munich, East/West rooftop system. Layout plan and DC plugs were done in summer 2022. Electrical installation of Huawei hybrid inverter, smart meter and 5kWh Huawei battery in 2023. Commissioning in October 2023. Electrical layout Huawei hybrid inverter and battery DC junction box with SPD Smart meter, RCD and MCB, single phase West East